300 contractors quit project

By Lokmat English Desk | Updated: June 23, 2024 23:10 IST

300 contractors quit projectThe GVPR company has been complaining about a lack of skilled manpower for the ...

Open in App

300 contractors quit project

The GVPR company has been complaining about a lack of skilled manpower for the past three years. The agency which provided the manpower did not get the money, therefore, it withdrew from the project. So far, 300 small and big contractors have left the work of GVPR.

Box

Digging of 19 city roads

About 19 roads in the city were dug up by GVPR to lay water pipes. The selection of concrete roads was done. There is a question as to who will re-construct after digging roads.

If the GVPR gives an assurance to pay the repair amount to the CSMC, it will repair roads.

But, there has been no decision on this for the past few months. Cement concrete roads built

in crores of rupees are in bad condition and minor accidents are happening there.

Box

Present work status of the scheme

Project cost: Rs 2740 crores

--Fund received so far: Rs1424 crores

--Fund paid to GVPR: Rs 1130 crores

--Dues of others with GVPR: Rs 400 Cr

--Work completion deadline: February 2024

--Main pipeline work: 38 km

--Remaining pipeline work: 6 km.

--Water pipeline laid in the city: 775 out of 1911

--Water tanks to be constructed: 53

--Construction of water tanks completed: 08

Box

Why does work completion appear impossible on time?

The rainy season is going on. The claim to construct one km main water line per month seems false. Jackwell's work is still in the basement. The permission from the Environment and Forest Departments was received late. There is no roadmap to complete the work of 45 water tanks in the city by the end of December. There is no planning for laying an internal water pipeline.

It is not decided who will repair the dug roads. The Government has given 50 per cent of the total amount. It is not yet known when the remaining amount will be received. Considering all these facts, it seems that the work will not be completed by December 2024.

Open in App

Related Stories

NationalHaryana CM Nayab Singh Saini Announces Rs 50 Lakh Compensation, Job for Family Member of Navy Officer Killed in Pahalgam Terror Attack

InternationalHamas delegation arrives in Cairo for Gaza ceasefire talks

Other SportsOlympics is making golf less elitist and more for the people, says R&A’s Roger Bathurst

InternationalPresident Murmu attends Pope Francis' funeral in Vatican City

EntertainmentWhen Satyajit Ray spoke about his ambition of adapting ‘Mahabharata’ to screen

Aurangabad Realted Stories

AurangabadCSMC calls for all-party meeting to avoid defacing city's beauty

AurangabadPolitical dispute leads to caste-based abuse against female office bearer

AurangabadTrainee dies during work at solar panel installation

AurangabadUddhav sena holds empty water pot procession due to water crisis

Aurangabad'Vividhā' dance performances and 'Prekshā' exhibition on World Dance Day