Fate of new water supply scheme hangs in balance!

By Lokmat English Desk | Updated: July 9, 2024 22:05 IST

Lokmat News NetworkChhatrapati Sambhajinagar:Political pressure is being exerted on the Maharashtra Jeevan Pradhikaran (MJP) to complete the ...

Open in App

Lokmat News Network

Chhatrapati Sambhajinagar:

Political pressure is being exerted on the Maharashtra Jeevan Pradhikaran (MJP) to complete the new water supply scheme (valuing Rs 2,740 crore) by December 2024. Although political leaders are insisting on the water project by keeping an eye on the upcoming assembly elections, however, the deposition of only Rs 55 crore in the bank account is worrying MJP. Hence it has requested Rs 835 crore aid from the Chhatrapati Sambhajinagar Municipal Corporation (CSMC) to complete the project.

To quench the city's thirst, work on a new water supply scheme is underway. So far, Rs 1,424.17 crore has been received from the Central and State Governments for this scheme. The CSMC transferred this fund to the MJP. Out of this, the MJP had spent Rs 1,368 crore on the work completed so far. Meanwhile, numerous bills have been submitted by the contractor company, which continuously demands payment. Meanwhile, the MJP has only Rs 55.35 crore in its bank account. To complete the scheme, MJP needs Rs 835 crore more. Hence it expects this fund to be provided by September or October. The MJP has also demanded a 3 percent service tax on this scheme, which means at least Rs 900 crore will be required. The MJP executive engineer Deepak Koli confirmed that the office had sent a letter regarding this to the CSMC last month.

Scheme Design

In the Rs 2,740 crore project, the Central Government will provide 25 pc (Rs 685 crore); the state government grant is set at 45 pc ( Rs 1,233 crore), and the municipal corporation's share is determined to be 30 pc (Rs 822 crore). The CSMC has already informed the government that it does not have funds available. In response to this, the state government had assured the municipal corporation that it would provide a 'soft loan' to it to contribute its share in the project.

No Provision

Political representatives are holding a series of meetings to ensure that the scheme is completed by December 2024. However, none of them is willing to take responsibility for securing the financial provisions for the scheme. Officials are indicating that if the municipal corporation's share is not provided on time, the scheme could be delayed by several more months.

Box

Why MJP needs Rs 835 crore?

Rs 150 crore - For contractor’s payment due to extraordinary price increase

Rs 70 crore - Water supply rejuvenation scheme

Rs 149 crore - For undertaking mechanical works

Rs 21 crore - For other mechanical works

Rs 500 crore - Funds required from June to December.

Open in App

Related Stories

NationalPeace Committee urges Telangana CM to take initiative for talks with Maoists

EntertainmentJennifer Winget wraps up shooting for mystery thriller with Parineeti Chopra; check pics

NationalHooch tragedy averted as 2,240 litres of pilfered extra neutral alcohol seized: Punjab Minister

MumbaiMumbai: Three Arrested for Assaulting Police at Checkpoint in Pydhonie

NationalPahalgam attack: CDS Anil Chauhan and Rajnath Singh meet amid India-Pak tension

Aurangabad Realted Stories

AurangabadChhattisgarh woman ends life at relative's house; case registered

AurangabadMurtizapur cylinder Blast: Woman succumbs to injuries

AurangabadOnline registration for TAIT-2025 commenced

AurangabadWhat is TrueBeam and how will citizens benefit?

AurangabadGovernment boosts cancer care and medical education