City
Epaper

Frequent snags in old pipelines paralyse new water supply schedule

By Lokmat English Desk | Updated: January 27, 2023 22:25 IST

Aurangabad:The new water supply schedule approved by the High Court has been disrupted, for the past few days, ...

Open in App

Aurangabad:

The new water supply schedule approved by the High Court has been disrupted, for the past few days, due to the frequent emergence of technical snags like damage to the old water pipeline, disruption in water supply due to a power cut or technical snag, etc. Meanwhile, the Aurangabad Municipal Corporation (AMC), is unable to supply water on a gap of three days and five days to the citizens. Moreover, the disturbance in the water supply schedule caused a sudden spike in the number of complaints from the residents. The AMC has claimed that it is trying its best to restore the approved water schedule at the earliest.

As reported earlier, the AMC lifts 100 MLD and 56 MLD of water from the Jayakwadi Dam (Paithan) through two main pipelines of width 1400 mm and 700 mm and supplies it to the residents of Aurangabad. Ironically, these pipelines completed their life spans, 20 years ago. As a result, every week or the other, a technical snag takes place in pipeline stretches between Jayakwadi and Nakshatrawadi or sometimes gets burst and disrupts the city water supply.

It may be noted that, on the intervening night of Tuesday and Wednesday, the CT conductor from the 33 KV sub-station at Pharola pumphouse got damaged due to sparking. The snag occurred as there was a heavy downpour in the district on Tuesday night. Later on, the AMC and the MSEDCL staff swung into action and repaired the snag in six hours. The lifting of water till the ESRs got started by 4 pm, and then the distribution in the city resumed after a couple of hours.

Supply delayed by one day: AMC

As per the Aurangabad Bench of Bombay High Court order, the AMC prepared the plan to distribute tap water to 60 per cent of the residents on a gap of three days (on the fourth day) and to 40 pc of residents on a gap of five days (on the sixth day) on a rotation of every fortnight. The civic administration claimed of providing water as per the new schedule for 23 days. The supply schedule got delayed by one day after the technical snag says AMC officials. However, the complaints from the citizens started to increase due to the delay. The linemen, junior engineers and an executive engineer are unable to convince the complainants.

Tags: High CourtAurangabad municipal corporationHong kong high courtAurangabad aurangabad municipal corporationKenyan high courtAMCAurangabad Bench of Bombay High Court
Open in App

Related Stories

NationalCan Mother-in-Law File Case Against Daughter-in-Law Under Domestic Violence Act? Here’s What Allahabad High Court Rules

NationalOdisha: High Court Grants Divorce Over Wife’s Mental Harassment and Suicide Threats

MumbaiBombay HC Upholds Divorce Over Spouse’s Suicide & Imprisonment Threats

NationalHC Directs Centre to Decide on Renaming India to Bharat or Hindustan

NationalMP HC Sides with Husband in Marital Dispute, Says Spouses Must Maintain Respect in Conversations

Aurangabad Realted Stories

AurangabadBJP focuses on building social harmony

AurangabadYoung woman robbed again in Same Area

AurangabadAvoid wild comments on ‘toxic parenting’

AurangabadMumbai-Nagpur high-speed rail project stalls as land acquisition office shut down

AurangabadUDD issues notification of approved City Development Plan