GAIL completes laying over 97.6% pipeline of Pradhan Mantri Urja Ganga

By ANI | Updated: April 13, 2025 17:56 IST

New Delhi [India], April 13 : GAIL (India) Limited has completed the laying of over 97.6 per cent of ...

Open in App

New Delhi [India], April 13 : GAIL (India) Limited has completed the laying of over 97.6 per cent of the integrated JagdishpurHaldiaBokaroDhamra Pipeline (JHBDPL), popularly known as "Pradhan Mantri Urja Ganga," which will carry Natural Gas to the eastern and Northern parts of India.

Of this, almost 96.6 per cent has been put under commercial operations, the state-owned company said in a statement.

The integrated JHBDPL including Barauni - Guwahati Pipeline having an authorized pipeline length of 3,306 km passes through Uttar Pradesh, Bihar, Jharkhand, Odisha, West Bengal and Assam.

Presently, 3,227 km of pipeline section has been laid and 3,119 km of Pipeline Section including Phulpur - Dobhi - Bokaro - Durgapur, Bokaro - Angul - Dhamra, Dobhi - Barauni - Guwahati Pipeline sections, have already been put under commercial operation, the company said.

The pipeline is presently transporting 12.26 Million Standard Cubic Meter Per Day (MMSCMD) of Natural Gas including supplies to four fertilizer plants, two refineries (Barauni and Paradip refineries), industrial consumers and 32 City Gas Distribution (CGD) networks including Varanasi, Patna, Ranchi, Jamshedpur, Bhubaneshwar, Cuttack, Kolkata etc. along pipeline route.

With respect to the Durgapur - Haldia Section (294 km), GAIL has already put 132 km of the Pipeline section upto Kolkata under commercial operation.

Further out of balance 162 km of pipeline section to Haldia, 103 km of pipeline laying has been completed. GAIL is also laying Dhamra - Haldia Section having an authorized pipeline length of 240 km of which GAIL has already laid 198 km of pipeline.

Due to limited availability of Right of Use (RoU), the completion of Durgapur - Haldia Section and Dhamra - Haldia Section of JHBDPL expansion is being extended from March 2025 to December 2025, the company statement added.

With the completion of balance section of Durgapur - Haldia and Dhamra - Haldia Pipeline, GAIL will transport Natural Gas to Haldia refinery, CGD Howrah, Hooghly, Purba Medinipur, Paschim Medinipur and other industrial consumers along the pipeline route.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

CricketRoyal Challengers Bengaluru tops point table after six-wicket win over Delhi Capitals

FootballLiverpool becomes Premier League champions for 2024-25 season

CricketIPL 2025: Heated Exchange Between Virat Kohli and KL Rahul During RCB vs DC Match; Video Goes Viral

Other SportsI was desperate to win for the most beautiful club in the world, says Liverpool captain Van Dijk on PL triumph

NagpurNagpur Road Rage: 21-Year-Old Truck Driver Stabbed to Death for Overtaking in Maharashtra

Business Realted Stories

BusinessSolid monetary frameworks helped emerging markets navigate recent crises: Gita Gopinath

BusinessPiyush Goyal lashes out at Big Pharma for evergreening patents

BusinessSEBI joins DigiLocker to reduce unclaimed assets, protect nominees’ interests

BusinessOver 170 million lifted above poverty line in India, Modi government and Congress claim credit

BusinessIndia, as fastest growing economy, is ideal investment destination: RBI Governor