Mumbai: RTI Reveals BMC Fines Contractors Rs 35 Crores for Coastal Road Project Delays

By Amit Srivastava | Updated: August 5, 2024 17:30 IST

The Brihanmumbai Municipal Corporation (BMC) has imposed fines amounting to only Rs 35 crores on contractors for delays in ...

Open in App

The Brihanmumbai Municipal Corporation (BMC) has imposed fines amounting to only Rs 35 crores on contractors for delays in Mumbai’s Coastal Road Project. This information was revealed through a Right to Information (RTI) request by civic activist Anil Galgali. The ambitious Mumbai Coastal Road Project has missed its deadline, with no updates on a new deadline. In response to the RTI query, the BMC stated that fines totaling Rs 35 crores were imposed on the contractors due to project delays.

RTI activist Anil Galgali sought various details from the BMC regarding the Mumbai Coastal Road Project. The Coastal Road Project Department of the BMC informed Galgali that the project is divided into three parts: Under Part 1, the work from Priyadarshini Park to Baroda Palace has been awarded to M/s Larsen & Toubro. A fine of Rs 11.63 crores has been imposed. The original deadline for completing Part 1 was October 12, 2022. This work has been extended three times: June 9, 2023, September 10, 2023, and May 22, 2025.

Under Part 2, the work from Baroda Palace to the southern end of the Bandra Worli Sea Link has been awarded to M/s HCC-HDC. A fine of Rs 16.13 crores has been imposed. The original deadline for completing Part 2 was October 15, 2022. This work has been extended three times: October 6, 2023, October 7, 2023, and October 25, 2024.

Under Part 4, the work from Princess Street to Priyadarshini Park has been awarded to M/s Larsen & Toubro. A fine of Rs 7.25 crores has been imposed so far. The original deadline for completing Part 4 was October 12, 2022. This work has been extended three times: May 25, 2023, November 26, 2023, and April 2, 2024. Currently, 91% of the work has been completed, and the project is in its final stages. Larsen & Toubro sent a written request to the BMC on July 23, 2024, seeking an extension of 181 days, citing eight reasons for the extension.

According to Anil Galgali, the fines imposed are low compared to the increase in project costs. Contractors aim to secure ambitious projects like the Coastal Road but often fail to complete them on time, leading to increased costs. These additional expenses are ultimately covered by the taxes paid by ordinary Mumbaikars.

Tags: Coastal Road projectrtimumbaiContractors complaints departmentMaharashtra NewsBMC
Open in App

Related Stories

NashikNashik: 20-Year-Old Woman Killed in Leopard Attack in Dindori Taluka

NashikSimhastha Authority to Be Established in Nashik: Eknath Shinde Unveils Plans in Mumbai Meeting

NashikNashik Water Crisis: Low Pressure, Tankers Deployed, Citizens Protest Over Lack of Supply

MumbaiIqbal Kaskar, Dawood Ibrahim’s Brother, Acquitted in 2017 Thane Extortion Case by Mumbai Court

MumbaiMumbai Local Train Accident: 40-Year-Old Man Dies After Falling Off the Train Near Dombivli Station

Mumbai Realted Stories

MumbaiMumbai Mega Block on April 27, 2025: Local Train Services To Be Affected on Western and Harbour Lines on Sunday

MumbaiMumbai Weather Update: IMD Predicts Dry Spell for Next Two to Three Days, Despite of Light Rainfall

MumbaiMumbai Crime: Jain Temple in Sewri Burgled, Thief Steals Valuables Worth Rs 7.15 Lakh

MumbaiMumbai Fire Accident: Massive Fire Engulf in Andheri Ground Plus Eight Storey Building, One Dead, Six Hospitalised

MumbaiMumbai Water Cut: Water Supply to Be Suspended For 24-hours in Ghatkopar and Kurla; Details Inside