Adani seeks help from Kerala govt on Vizhinjam Port

By IANS | Updated: September 13, 2019 16:30 IST

With the deadline for completion of the Vizhinjam Port project fast approaching in December, Adani Vizhinjam Port Pvt Ltd (AVPPL) has sought support from the Kerala government as the work at the port site is moving at a slow pace.

Open in App

AVPPL owner Gautam Adani at the time of the commencement of the project on December 5, 2015, had said that the first ship will berth there on September 1, 2018, in a record time of less than 1,000 days. But this deadline was missed. And with things moving at a snail's pace, meeting the deadline of December 4, 2019 also seems to be difficult.

As per the agreement, AVPPL is duty bound to pay a specific sum for each day of the delay.

Sources have said that three letters written by AVPPL to the state government were ignored. After the fourth letter, the Kerala government has decided to set up a committee to look into the matter.

The AVPPL has told the Kerala government that it will commission the project in October 2020, but for that it wants help in a big way, as there is a serious shortage of limestone required for building the breakwaters.

While the total length of the breakwater is 3.1 km, all that has been constructed till now is a mere 640 metres. Even though there are 19 quarries, but the required sanctions for operations have come only for three. The work at the port has also been hampered due to certain local issues and adding to the delay are the floods of 2018 and 2019.

Former State Ports Minister K.Babu said that for some strange reason, the present Left government is not helping AVPPL.

"When I was at the helm of affairs, we used to hold regular review meetings and anything which the state government needed to do was taken up. As I was the Minister to ink the project, I took it up as my responsibility and till we were in office, things were smooth. But now this government has completed more than three years, things are not going as it should have happened in a major infrastructure project like this," said Babu.

According to the envisaged plan, this would be one of India's deepest ports and 80 per cent of the country's cargo trans-shipments will take place from here.

The international multi-purpose deep water seaport project estimated to cost Rs 7,525 crore was planned by the Oommen Chandy government in 2015 which signed an agreement with AVPPL.

The AVPPL, which was the lone bidder for the project, had sought a Rs 1,635 crore grant for it.

The project also requires 360 acres of land, of which 130 acres have been reclaimed from the sea. Also part of it is a 10.9 km long railway line.

According to the agreement, Adani will operate the port for 40 years, extendable by 20 more years, while the state government will get a portion of the revenue from the port after 15 years.

( With inputs from IANS )

Tags: Gautam AdaniBabukerala
Open in App

Related Stories

NationalKerala Shocker: Man Murdered By Brother in Drunken Brawl in Thrissur

NationalKerala: Over 20 Injured as Makeshift Gallery Collapses During Football Match in Kothamangalam

MumbaiDharavi Redevelopment: No More Extensions for Residents Who Missed Survey As Deadline Ends

National‘Lack of Sleep’: Kerala Software Engineer Dies by Suicide Due to Work Stress; Family Demands Action

NationalKerala Accident: Man Dies After Being Hit by Truck and Car While Rescuing Kitten on Busy Road

National Realted Stories

NationalKarnataka BJP MLA's 'violent' remarks against Robert Vadra trigger row

NationalIAF confirms object falling from sky on MP house as 'non-explosive store'; probe initiated

NationalRahul Gandhi, Congress should apologise for derogatory remarks against Savarkar: BJP's Ram Kadam

NationalTripura CM Saha holds key meeting with BJP, IPFT and TMP leaders

NationalPahalgam terror attack: Rajkot airport goes 24/7 as Pak shuts airspace for Indian flights