Amrapali case: SC refuses to recall 2019 orders

By ANI | Updated: June 29, 2021 13:40 IST

The Supreme Court on Tuesday in its judgement said that it did not recall the 2019 orders or revisit the issue as to whether the Noida-based La Residentia project is a part of Amrapali projects and therefore the unfinished housing projects -- in Noida and Greater Noida -- have to be completed as per its orders.

Open in App

The Supreme Court on Tuesday in its judgement said that it did not recall the 2019 orders or revisit the issue as to whether the Noida-based La Residentia project is a part of Amrapali projects and therefore the unfinished housing projects -- in Noida and Greater Noida -- have to be completed as per its orders.

The bench of the apex court, headed by Justice Uday Umesh Lalit passed a slew of directions in the case.

By today's judgement, the apex court at this stage rejected handing over the project to the National Buildings Construction Corporation (NBCC) and directed La Residentia Company to construct and complete the construction of 632 units.

The apex court said that however, certain directions are needed to secure the amounts. The company is entitled to continue construction. 632 flats will be allowed to be sold by the company at a fair price provided that all the documents (of the company) are counter signed by the receiver, appointed by the court.

However, the court had brought the construction of 632 units by giving certain directions so that the project completion work is monitored by the Court Appointed Receiver.

"All sale deeds to be signed by the Court Receiver. The amount would be deposited in name of the Court Receiver. Advances, if any, be given by the Receiver for the construction of these 632 Flats. Difference between Sale and Expenditure be deposited with Court Receiver," the apex court said in its order.

Justice Lalit concluded by giving thanks to Justice Ashok Bhushan for his contribution in the Amrapali case, as the Bench will now be reconstituted with a different combination. Though it was made clear in the end that the next date will be in next to next week and in the same manner, i.e., Mondays at 2 pm.

The sale price of unsold flats will be set by the Chartered Accountant and overseen by the Court Receiver.

After the court pronounced the verdict, M L Lahoty, a lawyer for many Amrapali home buyers, toldthat it is a big relief to the home buyers of La Residentia Project.

"It is big relief for the home buyers of the La Residentia Project, as the construction was stuck for a long time and completion will take place specially when the Reciever is monitoring," Lahoty told ANI.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: NBCC (India) LimitedUday umesh lalitSupreme CourtAshok Bhushan
Open in App

Related Stories

NationalPregnant Sunali Khatoon and Her Son, Deported as Bangladeshis, to Be Brought Back to India, Centre Tells Supreme Court

BusinessVodafone Idea Shares Jump by 2% As Government Reviews AGR Relief Proposal

NationalSupreme Court Orders Nationwide Digital Arrest Cases to Be Transferred to CBI

BusinessAnil Ambani's Reliance Power and Reliance Infra Stocks Fall After SC Issues Notice on Plea for Probe Into Alleged ADAG Bank Fraud

BusinessVodafone Idea Shares Jump 3% Today as Telecom Stock Rises 75% in Three Months Amid Strong Market Momentum

National Realted Stories

NationalGovt leveraging geospatial tech as national asset for Viksit Bharat: Jitendra Singh

NationalSatna HIV horror: Lapses in blood testing could be reason, says Congress MLA

NationalFerozepur-Delhi Vande Bharat Express to make halt at Barnala

NationalManipur Guv reaffirms commitment to inclusive development and indigenous heritage

NationalMere proof of victim's caste insufficient for conviction under SC/ST Act: Supreme Court