CCEA approves scheme on green energy corridor phase-II for intra-state transmission system

By ANI | Updated: January 6, 2022 18:00 IST

The Cabinet Committee on Economic Affairs on Thursday approved a scheme on Green Energy Corridor (GEC) Phase-II for Intra-State Transmission System (InSTS) which will help in achieving the target of 450 GW installed renewal energy capacity by 2030.

Open in App

The Cabinet Committee on Economic Affairs on Thursday approved a scheme on Green Energy Corridor (GEC) Phase-II for Intra-State Transmission System (InSTS) which will help in achieving the target of 450 GW installed renewal energy capacity by 2030.

It will lead to addition of approximately 10,750 circuit kilometres (ckm) of transmission lines and about 27,500 Mega Volt-Amperes (MVA) transformation capacity of substations, Union Information and Broadcasting Minister Anurag Thakur told the media after a meeting of Union Cabinet.

An official release said the scheme will facilitate grid integration and power evacuation of about 20 GW of Renewable Energy (RE) power projects in seven states - Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh.

The scheme is targeted to be set up with total estimated cost of Rs. 12,031.33 crore and Central Financial Assistance (CFA) @ 33 percent of the project cost i.e. Rs. 3970.34 crore.

The transmission systems will be created over a period of five year from 2021-22 to 2025-26. The Central Financial Assistance (CFA) will help in offsetting the intra-state transmission charges and in keeping the power costs down.

"The scheme will help in achieving the target of 450 GW installed RE capacity by 2030," the release said.

It said the scheme will also contribute to long-term energy security of the country and promote ecologically sustainable growth by reducing carbon footprint and generate large direct and indirect employment opportunities for both skilled and unskilled personnel in power and other related sectors.

This scheme is in addition to GEC-Phase-I which is already under implementation in Andhra Pradesh, Gujarat, Himachal Pradesh, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan and Tamil Nadu for grid integration and power evacuation of about 24 GW of renewal energy power and is expected to be completed by 2022.

The scheme is for addition of 9,700 ckm of transmission lines and 22600 MVA capacity of substations having estimated cost of transmission projects of Rs 10,141.68 crore with Central Financial Assistance (CFA) of Rs 4056.67 crore.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Cabinet Committee On Economic AffairsGreen energy corridorAnurag Thakur
Open in App

Related Stories

NationalDelhi Assembly Election 2025: Anurag Thakur Issues Chargesheet Against AAP National Convenor Arvind Kejriwal

NationalParliament Scuffle: Anurag Thakur and Other BJP MPs File Police Complaint Against Rahul Gandhi (VIDEO)

NationalNDA-INDIA Bloc Clash: Anurag Thakur and Other BJP MPs Reach Police Station To File Complaint in Parliament Scuffle Incident

NationalGovernment Announces New MSP for Rabi Crops: Wheat, Lentil, Mustard See Substantial Hikes

MumbaiMumbai-Indore Train Project: Cabinet Approves 309 Km Railway Line to Be Completed by 2028

National Realted Stories

NationalPoster controversy: Police disperse protestors in Jaipur, say situation under control

NationalGujarat: Vadodara woman duped of Rs 5.61 lakh in visa scam, complaint filed

NationalRetaliatory actions against Pak reflect India’s strong policy against those promoting terror: Raksha Khadse

NationalMP: CM holds meeting on law and order, identified 228 Pak citizens to leave nation by Sunday

NationalRoad rage case: K’taka HC restrains police from initiating coercive action against IAF wing commander