Jiribam - Imphal new line railway project in Manipur achieved 93 per cent progress

By ANI | Updated: April 2, 2023 22:35 IST

Guwahati (Assam) [India], April 2 : The Jiribam - Imphal new line railway project, one of the crucial connectivity ...

Open in App

Guwahati (Assam) [India], April 2 : The Jiribam - Imphal new line railway project, one of the crucial connectivity projects for the North-eastern region achieved progress of 93.30 per cent, officials said on Sunday.

"The works for this new line railway project, among other connectivity projects, is also going on in full swing to connect Imphal, the capital city of Mpur to the rest of the country. The Jiribam - Imphal project has already achieved physical progress of 93.30 per cent," Sabyasachi De, CPRO of NF Railway said.

The NF Railway CPRO said that construction of the Jiribam - Imphal railway project involves multiple tunnels and bridges in tough terrains which are stretched at more than 111 km length.

"The total length of tunnels in this project is 61.32 km out of which 59.11 km of tunnelling works have already been completed. The project will have a total of 11 major bridges and 137 minor bridges, out of which work for 05 major bridges and 101 minor bridges have been completed so far. The tallest pier railway bridge in the world with a height of 141 meters is also being constructed in this project and nearing completion," Sabyasachi De said.

Indian Railways is significantly contributing towards the transformation of the Northeastern states by executing several new railway line projects.

Constructing new railway lines to connect all the state capitals of the northeastern region is going on under capital connectivity projects.

that, the Jiribam - Imphal new line railway project is one of the crucial connectivity projects for the Northeastern region that is at an advanced stage of completion.

He further said that the section from Jiribam to Khongsang has already been commissioned for train service.

"After completion of the entire project, the present road journey time of about 10 hours to reach Imphal from Jiribam will get reduced to 2.5 hours by railways. NF Railway is putting their full effort by working 24X7 for the completion of this project with all the challenges like heavy rainfall and other logistic hindrances. The new rail project will provide enhanced connectivity to the people of Mpur, help grow small-scale industries in the area and boost the tourism of the state," Sabyasachi De further said.

The NF Railway, CPRO also said that It will also help in receiving essential commodities faster by the state and help the state local producers to export their produces outside the state faster.

"Economy of the state will receive a boost," he added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Nf railwayNf railway cproSabyasachi deguwahatiImphalDoul govinda temple
Open in App

Related Stories

CricketAnother Security Breach in IPL 2025: Fan Runs Onto Field, Falls at Riyan Parag’s Feet During RR vs KKR Match in Guwahati (Watch Video)

CricketKKR vs RR, IPL 2025 LIVE Streaming: When and Where To Watch Today’s Kolkata Knight Riders vs Rajasthan Royals Match

NationalAssam: Shops To Be Allowed To Remain Open 24 Hours in Guwahati, Dibrugarh, Silchar, Says CM Himanta Biswa Sarma

NationalIndia's Got Latent Row: Ashish Chanchlani Granted Interim Protection From Arrest in Assam Police FIR

NationalManipur Violence: Mobile Internet Ban Extended Till December 5 in 9 Districts

National Realted Stories

NationalSajad Lone says Pahalgam massacre 'an attack on identity of Kashmiris'

National'Terror will never win': Former UK PM Rishi Sunak condemns terrorist attack in J&K's Pahalgam

NationalPahalgam terror attack: Antigua PM writes to PM Modi; extends condolences

NationalED attaches Sahara's 'benami' properties valued at Rs 1,538 crore across India

NationalUN chief strongly condemns Pahalgam terror attack