NGT slaps Rs 13.95 Cr fine on Mahagunpuram project builders in Ghaziabad

By IANS | Updated: February 10, 2022 12:35 IST

New Delhi, Feb 10 The National Green Tribunal has slapped a penalty of Rs 13.95 crore on builders ...

Open in App

New Delhi, Feb 10 The National Green Tribunal has slapped a penalty of Rs 13.95 crore on builders of the Mahagunpuram project in Ghaziabad for blatant violation of environmental norms.

A bench of NGT chairperson Adarsh Kumar Goel recently directed Mahagun Real Estate Pvt Ltd, promoters of the project to deposit environmental compensation of Rs 13,95,50,000/- with the State Pollution Control Board.

The order said that the construction and cost of land received from the project proponent amounted to Rs 279.10 crore. In this Rs 74.92 crore has been shown as the cost of land and Rs 204.18 crore as the cost of construction.

As per the order of the Supreme Court and assessing the gravity of violations made by the project proponent, environmental compensation in the present matter has been computed at five per cent of the project cost, which has been stated as a general law by the apex court.

The bench asked the builder to submit a detailed Environment Clearance utilisation plan for 50 per cent of the environmental compensation imposed primarily on the improvement of the environment within the society and part of it may be utilised with district authorities.

The tribunal directed Ghaziabad Development Authority (GDA) to take further action in accordance with law and submit a compliance report within 15 days.

Earlier on December 10, 2021, as per the directions of the green court, the GDA has submitted a report, in which it pointed out the violations of norms.

It was observed that encroachment in some way or other has been done on green belts, including the main entrance road of the society.

A temple has been built on part of the green belt defined as Pocket D on the map approved by Ghaziabad Development Authority, it noted.

According to the complainant, the plot area is 54,630 sq. meters. As per the environmental clearance, 15 per cent of the total plot area shall be compulsorily made available for green belt development, including the periphery of the green belt. However, the builder has not kept the 15 per cent green belt.

The matter has been posted for further hearing on March 25.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: National Green TribunalMahagun real estate pvt ltdAdarsh Kumar Goel
Open in App

Related Stories

Navi MumbaiNavi Mumbai: RTI Exposes CIDCO’s Delay in Restoring DPS Flamingo Lake

Navi MumbaiNGT Slaps Rs 10,000 Fine on TTD for Delay in Responding to Environmental Concerns in Ulwe Temple Case

Navi MumbaiNavi Mumbai: NGT Issues Notice to MIDC Over Environmentalist's Plea to Protect Green Patch with 200 Trees

ThaneThane News: Environment Activists Sound Alarm Over Illegal Stone Quarrying Near Skyscrapers

NashikNashik: Collector's Report Stating Trimbakeshwar Not in Eco-Sensitive Zone Shocks Environmental Activists

National Realted Stories

National'Terrorists behind Pahalgam massacre will not be spared', says Bengal BJP chief

NationalHindu Pakistani nationals holding long term visas exempted from visa revocation

NationalPresident Droupadi Murmu to Attend Pope Francis' Funeral in Vatican City on April 26

NationalEmbankment construction by B'desh: Cong urges Tripura govt to resolve issue

NationalPahalgam terror attack: Indus Waters Treaty kept at abeyance, India informs Pak