Work on Mumbai-Ahmedabad Bullet Train Project progressing at rapid pace: Centre

By IANS | Updated: December 29, 2024 12:45 IST

New Delhi, Dec 29 Work is progressing at a rapid pace on the Mumbai-Ahmedabad Bullet Train Project with ...

Open in App

New Delhi, Dec 29 Work is progressing at a rapid pace on the Mumbai-Ahmedabad Bullet Train Project with bridges built across 13 rivers and several highways and multiple railway lines being crossed through seven steel and prestressed concrete bridges, according to the year-end review of Indian Railways.

Over 243 km of viaduct construction has been completed under the project, along with 352 km of pier work and 362 km of pier foundation work.

Track construction in Gujarat is progressing rapidly, with RC (Reinforced Concrete) Track Bed construction underway in Anand, Vadodara, Surat, and Navsari districts. About 71 track km of RC track bed construction has been completed, and welding of rails has commenced on the viaduct.

In Maharashtra, the first concrete base slab for the Mumbai Bullet Train Station has been successfully cast at a depth of 32 metres, equivalent to a 10-storey building. Work on the 21 km tunnel between Bandra-Kurla Complex (BKC) and Shilphata is underway, with an Intermediate Tunnel (ADIT) of 394 metres completed to facilitate main tunnel construction.

Construction of seven mountain tunnels using the New Austrian Tunnelling Method (NATM) is progressing in the Palghar district. The only mountain tunnel in Gujarat has already been successfully completed.

“The 12 stations along the corridor, designed with thematic elements and energy-efficient features, are under rapid construction. These user-friendly and energy-positive stations are designed to provide a world-class passenger experience while prioritizing sustainability,” the review states.

Meanwhile, Indian Railways has set a target of becoming a Net Zero Carbon Emitter by 2030. As of November 2024, approximately 487 MW of solar plants (both rooftop and ground-mounted) and about 103 MW of wind power plants have been commissioned, the review states.

Additionally, 100 MW of Renewable Energy - Round the Clock (RE-RTC) has also started flowing and approximately 2014 MW of renewable capacity has been tied up, it added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

NationalPoster controversy: Police disperse protestors in Jaipur, say situation under control

NationalGujarat: Vadodara woman duped of Rs 5.61 lakh in visa scam, complaint filed

NationalRetaliatory actions against Pak reflect India’s strong policy against those promoting terror: Raksha Khadse

AurangabadFamily booked in another illegal moneylending case

Aurangabad155 wedding guests suffer food poisoning in Kannad tehsil

National Realted Stories

NationalMP: CM holds meeting on law and order, identified 228 Pak citizens to leave nation by Sunday

NationalRoad rage case: K’taka HC restrains police from initiating coercive action against IAF wing commander

NationalBihar: Senior IAS officer KK Pathak relieved, set to join Central govt

NationalInimical forces may spread false propaganda to disturb peace: Nagaland Police

NationalMadhya Pradesh: Three children drown in dam