CAG audit highlights 'inefficiencies' in DRDO's planning process

By IANS | Updated: December 22, 2022 21:50 IST

New Delhi, Dec 22 A CAG report has brought out "inefficiencies" in the planning process by the DRDO ...

Open in App

New Delhi, Dec 22 A CAG report has brought out "inefficiencies" in the planning process by the DRDO as well as raising issues of inadequate monitoring of the "mission mode" projects by it.

Mission mode (MM) projects are taken up by the DRDO as high-priority projects based on specific user requirements with a definite time frame for their completion, as these depend on technologies that are already available, proven, and readily accessible within DRDO/India or from abroad at a short notice.

However, the CAG Performance Audit on 'Management and Outcome of Mission Mode Projects in DRDO' - Union Government (Defence Services) - DRDO, tabled in Parliament on Wednesday, has highlighted that despite the fact that MM projects have a very high outcome certainty due to ready availability of underlying technology, there were considerable delays in initiation and sanction of such projects by DRDO.

"In 119 out of 178 projects, the original time schedules could not be adhered to. In 49 cases, the additional time was in fact more than 100 per cent of the original time frame. Overall, the delays ranged from 16 to 500 per cent and extension of time for completion of projects was taken multiple times. Time overruns in completion of MM projects, where technologies are either available or easily accessible, defeats the purpose of taking them up as an MM project," said the report.

The report has also mentioned that out of 86 projects declared as successful during January 2010 and December 2019, in 20 projects involving an expenditure of Rs 1,074.67 crore, one or more key objective(s)/parameter(s) was/were not achieved.

Instead of seeking extension of time to achieve all the key objectives/parameters of the project proposal, these projects were closed as successful. The report has pointed out that the DRDO had taken up 15 projects costing Rs 516.61 crore to accomplish the unachieved objectives of similar earlier closed projects declared as successful by it.

The performance audit of MM Projects, inter-alia, brought out time and cost overrun in completion of projects, irregular closure of projects declaring them successful despite non-achievement of one or more key objectives/parameters, and taking up of new projects for realising the unachieved objectives of earlier closed projects declared as successful.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: DrdoDefence Services
Open in App

Related Stories

NationalDRDO Conducts Successful Field Firing Trials of Indian Light Tank ‘Zorawar’ (Watch Video)

NationalRam Narain Agarwal Passes Away: Renowned DRDO Scientist and Father of Agni Missiles Dies at 84

NationalDRDO Successfully Flight-Tests Phase-II Ballistic Missile Defence System (Watch Video)

NationalDRDO-Made Chinook Helicopter Displayed at 2020 Defense Expo in Lucknow Reported Missing

NationalGujarat Honey Trap Case: Man Spying for Pakistan’s Intelligence Agency ISI Arrested in Bharuch

Politics Realted Stories

Maharashtra'Unity Not Just for Elections': MNS Leader Sandeep Deshpande on Possible Thackeray Alliance

PoliticsMurshidabad Violence: Shehzad Poonawalla Slams Yusuf Pathan Over Tea Post, Says, “As Hindus Get Slaughtered…”

PoliticsTamil Nadu Assembly Elections 2026: BJP-AIADMK Join Hands, Palaniswami To Lead Alliance, Says Amit Shah

Politics‘No Injustice to Muslims’: Shiv Sena Leader Manisha Kayande Slams Opponents of Waqf Amendment Bill

NationalParliament Passes Waqf Amendment Bill: Two JDU Leaders Resign Over Party's Support