Mumbai-Ahmedabad bullet train project progressing well: Railways

By IANS | Updated: September 5, 2020 18:05 IST

New Delhi, Sep 5 The Indian Railways on Saturday said that the 508-km Mumbai-Ahmedabad High Speed Rail project, ...

Open in App

New Delhi, Sep 5 The Indian Railways on Saturday said that the 508-km Mumbai-Ahmedabad High Speed Rail project, popularly known as the 'Bullet Train' project, was progressing well, but the real timeframe for the completion of the project can be gauged within the next three to six months when the status of land acquisition will be ascertained.

Addressing a virtual press conference, Railways CEO V.K. Yadav said, "While 82 per cent of the land has been acquired in Gujarat, in Maharashtra land acquisition is only at 23 per cent." He said that in a linear project like the bullet train, work can only begin when a certain amount of land is available.

"We are hoping that within the next three to six months, we will be able to get to that point. Our designs are ready and we are set to go. It is true that the tenders and land acquisition was delayed a bit due to the Covid-19 pandemic, but I can say that the project is progressing well," Yadav said.

He asserted that as the Covid-19 situation improves, the Railways will be able to start the bidding process within the next three to six months.

He said, "We will be able to get the status of land acquired and then we will be able to provide a real timeframe for the completion of the project."

( With inputs from IANS )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Indian RailwaysMinistry of indian railwaysIndian railways ministryIndian railway networkBangladesh railways
Open in App

Related Stories

MumbaiMumbai–Goa Travel Boost: LTT–Karmali Express Extended to Madgaon for Festive Rush till January 15 - Check Timings & Other Details

NationalKonkan Railway Announces Christmas–New Year 4 Special Trains From December 16 to January 7; Check Schedule

NationalIndian Railways Loco Pilots Demand Work-Hour Limits After IndiGo Crisis

NationalIndiGo Flight Cancellations: Indian Railways Deploys 116 Extra Coaches Across 37 Trains to Ease Travel Disruptions

NationalIRCTC Launches International Tour Packages, Including Europe and Dubai, Under MOSD Tour Model

Politics Realted Stories

MumbaiWho Is Tejasvee Ghosalkar? Shiv Sena UBT Leader and Former Corporator Joins BJP Ahead of BMC Polls

MaharashtraSanjay Raut Says Sena–MNS Already Together No Need Others Permission

MaharashtraBig Jolt to Sharad Pawar as Salil Deshmukh, Son of Anil Deshmukh, Quits NCP-SP

PoliticsEknath Shinde Issues Strict No-Crossover Order After Meeting Amit Shah; Directive Communicated to All Shiv Sena Leaders

MaharashtraBMC Elections 2025: Devendra Fadnavis Says Clarity on Seat-Sharing Will Emerge in Two Days